Monenco Signed a Contract of “Power System Study and Relay Coordination for Qarn Alam Power Plant Co-Generation”

Recently, "Power System Study and Relay Coordination for Qarn Alam Power Plant Co-Generation" project has been awarded to Monenco Consulting Engineers by Petrofac & PDO (Petroleum Development Oman). Qarn Alam Power Plant is located in the independent power system of Petroleum Development Oman (PDO). The project scope includes installation and commissioning a new GEF9E Gas

Monenco Recently signed a contract of “Consultancy Services for Design and Tendering Services for Construction of New 3×20 MVA at Mabelah South Phase 9, Primary Substation”

Monenco Consulting Engineers Recently signed a contract of “Consultancy Services for Design and Tendering Services for Construction of New 3x20 MVA at Mabelah South Phase 9, Primary Substation” in Oman with Muscat Electricity Distribution Company. In this project, Monenco is responsible to render following services: Design Providing survey and study report Confirmed PSS FGL Soil

Monenco signed a contract of “Consultancy Services for Design and Tendering Services for Upgrading of Mawalleh North PSS and Al Hail PSS from 2*20 MVA to 3*20 MVA”

Monenco Consulting Engineers Recently signed a contract of “Consultancy Services for Design and Tendering Services for Upgrading of Mawalleh North PSS and Al Hail PSS from 2*20 MVA to 3*20 MVA” in Oman with Muscat Electricity Distribution Company. In this project, Monenco is responsible to render following services: Design Providing survey and study report Confirmed

Monenco Consulting Engineers Recently signed a contract of “Consultancy Services for Design and Supervision on Construction of Duqm 33/11 KV Primary

Recently, “Consultancy Services for Design and Supervision on Construction of Duqm 33/11 KV Primary Substation” was awarded to Monenco Consulting Engineers by Tanweer in Sultanate of Oman. This project is part of expansion of Duqm electrical network and the main purpose of this project is to construct a new primary substation in Duqm area in

Certificate of Appreciation from Oman Electricity Transmission Company

HSE Certificates of Appreciation have been awarded to Monenco on behalf of Oman Electricity Transmission Company (OETC) in Oman as described below: Best Performance in HSE Campaign 2019 for the project "Adding Third and Fourth Transformer at Airport Height Grid Station" 1.5 Million Safe Man-Hours for the project "Construction of New 132/33kV Ghala Height and

Commissioning of Ghala Project

The latest part of Ghala Project which was 132kV UG Cables from Ghala Heights Grid Station to Bousher Grid Station Circuit 1 & 2 was completed, Energized and Operated successfully in October 2019. The project was located in Muscat, Sultanate of Oman and Oman Electricity Transmission Company was the client. In this project, Monenco was responsible for basic design, conceptual design, project management

Commissioning of “Development of Airport Heights 220/132/33kV Grid Station Project”

In 2015, Oman Electricity Transmission Company (OETC) planned to develop existing 220/132/33kV grid station in Airport Heights, Muscat, Oman. This project is part of OETC’s target to expand and reinforce the power transmission and distribution networks in response to the loads growth and introduce new capacity into the network. In this regard, the Consultancy Services

Successfully Energized 132kV UG Cables from Ghala Heights to Bousher GS Ckt 1 & 2 (TN 43/2016)

Monenco have Successfully Energized 132kV UG Cables from Ghala Heights to Bousher GS Ckt 1 & 2 . The Brief of the Scope of the project is to Construct New 132/33kV Ghala Height Grid Station, and adding two 132kV GIS Bays at Bousher – 1 GS and connect Ghala and Bousher -1 via 132kV Cable

Holding a training course for experts and managers of Oman Electricity Network Operators in Oman

Monenco held a training course for two weeks for 20 experts and Managers of Oman Electricity Network Operators. In this training course, the Modern Technics of Network Operations as well as related challenges and proper solutions in the Normal and Emergency Conditions Were Presented.