132kV Portion Successfully Energized at A’salam GS

On Thursday  (15.11.2018) we have successfully energized 132kV Portion at A’salam  GS, which includes:

  • 125MVA Transformer –  03rd  & EAT-03
  • 125MVA Transformer –  04th  & EAT-04

The project scope is Adding 3rd and 4th Transformer – 132/33kV 125MVA – 2 Nos., 2 Numbers 500kVA EAT and 24 numbers 33kV GIS bays and 2 Nos 20 MVAR Capacitor banks, 132kV Cables and accessories and associated Control panels.

During the time of energization, the Client OETC operation team , Appreciated Monenco team’s effective execution, supervision and excellent management during the  execution and commissioning phase of the project.